Ladies Showers - progress at last
Report and pictures by Chris Grimmett - other pictures by Paul Meredith
The
March Committee meeting agreed that completion of Ladies Showers
would go ahead during the working week and that there would
be 3 cubicle showers installed. As there was a good deal
of work required to prepare the walls and floor, this had to
start over Easter so that concrete and render would have time
to dry out before tiling.
The first problem was how to remove the Galpinite which was
not only on the floor but had also crept up some of the walls.
Knowing the difficulties encountered in the Gents Showers, more
serious kit was obtained
|
|
|
John
Lister attacked the old shower partitions with an ancient but
effective air breaker and succeeded in demolishing the dreaded
Galpinite.
Brian got a little too close and nearly precipitated the election
of a new Warden at the Annual General Meeting
|
Various
people assisted with removal of the floor; Allan Richardson
is seen here with the heavy breaker.
As it was, there was an upper screed of Galpinite about 2 or
3 inches thick with a much thicker layer beneath it. It
was decided to remove only this upper layer and leave the bulk
intact.
Because of this, the showers floor will be higher than originally
planned, giving a problem with the height of the entrance, already
rather low
|
|
|
It
was decided that as the floor was going to be higher, then the
entrance would have to be enlarged by a similar or greater amount.
Unfortunately, this part of the wall is solid cast concrete
over the original stonework and it was very difficult to deal
with.
Not too much later, a large lump of concrete was removed using
an appropriate method; some ladies using the Gents Showers at
the time were forced to lie low for a short while during this
operation.
|
Careful
attention was paid to the size of the entrance in order that it
would fit ladies of differing vertical development.
Technical constraints meant that no such allowance could be made
in the x-axis and any ladies of girth greater than 84 inches will
scrape their bodywork as they enter the new showers.
|
|
|
Personal
Protective Equipment was issued to all taking part.
|
The old and very rotten window was replaced with
a double glazed unit. Allan Richardson assists Vince Allkins |
|
The floor and walls are now being concreted and rendered ready
for tiling and plumbing during the Working Week. Ladies
will be interested to know that the Committee decided against
a feature row of tiles in pink.
For those many of you who seem not to know when the main Working
Week takes place, the date is w/c Monday May 26th., although
work will start over the preceding weekend 24th. and 25th. Contact
Chris Grimmett cmg@goostrey.demon.co.uk
or Allan Richardson allan@caving.demon.co.uk
if you would like to come and help.
by Chris Grimmett
|
Pics from Paul Meredith
Harvey, Vince and Paul take samples of Galpinite away for analysis.
(Right)
Paul and Alex Meredith (with help from Haley) are shifting debris
while a Dobson works away in the corner.
(Below)
Vince and John apply several hundred horsepower.
(Below Right)
Kevin Diffey was on wheelbarrow duty!
|
|
|
|
|